I-10 East
Overnight
Sunday, Oct. 30 through Thursday, Nov. 3
9 p.m. each night to 5 a.m. each morning
· I-10 Eastbound will be reduced to one lane for approximately a half mile starting at the North Mesa Overpass.
Crews will be working on temporary shoring walls in the area. [Map 2]
Mesa
Daytime
Monday, Oct. 31 through Friday, Nov. 4
9 a.m. to 4 p.m. each day
· A right lane on North Mesa Street (SH 20) will be closed between Remcon Circle to Osborne Drive (in the direction traveling toward Doniphan Drive).
Crews will be boring and potholing for utilities. This area will continue to be the focus of intense work for the next several months while crews transform the intersection, including the I-10 bridge. [Map 2]
I-10 West
Overnight
Tuesday, Nov. 1
9 p.m. to 5 a.m.
· I-10 Westbound will be completely closed between the Executive Overpass and the Sunland Overpass.
This closure was first announced last week. Crews will be tackling various activities, including removing overpass signage, setting barrier, removing illumination poles, repairing potholes, replacing reflectors on barrier walls, and more. [Map 1]
Detour Route: Traffic will exit I-10 Westbound at Executive Center Boulevard (Exit 16), take North Mesa Street (SH 20) to Sunland Park Drive, then re-enter I-10 Westbound at the Sunland Park Entrance Ramp. Follow the detour signs in place.